Data centre power demand set to triple by 2035
Planned sites are growing larger, with many expected to surpass 500 megawatts.
Data centre electricity use is forecast to surge almost threefold by 2035. BloombergNEF reported that global facilities are expected to consume around 106 gigawatts by then.
Analysts linked the growth to larger sites and rising AI workloads, pushing utilisation rates higher. New projects are expanding rapidly, with many planned facilities exceeding 500 megawatts.
Major capacity is heading to states within the PJM grid, alongside significant additions in Texas. Regulators warned that grid operators must restrict connections when capacity risks emerge.
Industry monitors argued that soaring demand contributes to higher regional electricity prices. They urged clearer rules to ensure reliability as early stage project numbers continue accelerating.
Would you like to learn more about AI, tech and digital diplomacy? If so, ask our Diplo chatbot!